5th session of the international commitiee of exports

5TH SESSION OF THE INTERNATIONAL COMMITIEE OF EXPERTS

MOSTAR 26, 27, 28 OCTOBER 2000.

 

AGENDA - MOSTAR 26-28 OCTOBER 2000

Thursday 26. October  2000,

10.00-11.15       Opening of the session, presentation and adoption of the agenda of
the 5th session of the ICE ( Chairman-Professor Leon Pressouyre).

11.15-12.30       Presentation of the progress of the works and discussion ( Dr. Colin
     Kaiser UNESCO Representative in B&H, Messes. Cisic, Rozic and Pequeux PCU) .

12.30-14.00       Lunch

14.00-16.30       Presentation[1] of the draft final report on Geological investigations  prepared by  Joint Venture CONEX-Yeralti Aramacilik - (CONEX and Mr. Pequeux).

16.30-18.00       Discussion by ICE and adoption of the proposed project for strengthening of the foundation, or additional discussion with the contractor for better clarification of the project.

20.30                Official dinner organised by Mr. Colin Kaiser, UNESCO Representative in B&H and Professor Leon Pressouyre, The chairman of the ICE. (Hotel “ERO”). 

Friday, 27. October 2000

09.30-11.30       Presentation[2] by LGA company, responsible for Laboratory tests on stone, mortar, lead and iron
Presentation of the results of the laboratory tests on the  following ancient and new materials:
a) Old stone
b) New stone
c) Analysis of the old iron and proposal for the new composition of the iron 
d) Analyses of the different types of the mortars find in the structures of the Old  
    Bridge and proposal for the new composition of the mortar.
e) Analysis of the old lead and proposal for the new composition of the lead 
f)  Proposal regarding the eventual reuse of the old Tenelija stone in the structures  
    of the new bridge.

11.30-13.00       Discussion by ICE and adoption of decisions related to the results of the laboratory   
                        tests in the regard to the usage of tested and proposed materials.

13.00-14.30       Lunch

14.30-16.30       Presentation by General Engineering[3] - Design, Photogrametry and calculations.
Presentation consist of the following topics:
a)      the preliminary design for the old bridge which have to be
         discussed by the ICE
b)      preliminary calculations
c)      Other proposals and issues related to the calculation which have to be    
         raised and discussed during the presentation.

16.30-18.00       Discussion by ICE and adoption of the decisions or remarks related to the preliminary design of the Old Bridge. Only after agreement on phase A will General Engineering be able to begin with the Phase B of their assignment.

20.30                Official dinner organised by the Project Coordination Unit ‘ PCU

Saturday, 28. October 2000

10.00-11.30       Discussion on the reuse of the old stone, based on the presentations made by the LGA and General Engineering[4].
Discussion has to reach agreement the following points:
a)      To use old stone in the structural parts of the bridge or not.
b)      If old stone could be used in the structural parts, in which form: to be re-cut or 
         to be put in to the original position without additional treatment.
c)      For reuse old stone in non structural parts
            -To reuse the old stone in the previous positions if the location can 
              defined    insertion into new location .
d)      How to treat  old stone in the new structure.

11.30-13.0         a) Discussion on the process of  selection and pre-qualification of the contractors to
    be used for the bridge reconstruction.
b) Composition of the Evaluation committee.

13.00-14.30       Lunch

14.30-16.00       Preparation of the decisions and conclusions of the 5th session of the ICE.
                        Adoption of decisions. Proposal for the date for the 6th session .


[1] After the presentation the contractor (CONEX-YERALTY ARMACILIK)will leave the meeting room and wait for the eventual second call in order to clarify some of the questions raised by the members of the ICE . The Contractor’s team could not consist of more then three persons.

2 After the presentation the contractor (LGA) will leave the meeting room and wait for the eventual second call in order to clarify some of the questions raised by the members of the ICE . The Contractor’s team could not consist of more then three persons.

[3] After the presentation the contractor (General Engineering) will leave the meeting room and wait for the eventual second call in order to clarify some of the questions raised by the members of the ICE . The Contractor’s team could not  consist of more then three persons.

[4] The above mentioned companies are requested to be present in Mostar on 28 October, in order to respond to possible additional questions and requirements related to reuse of the old stone and other old materials.

Decisions of the 5th Session of the International Committee
of Experts for the Rebuilding of Stari Most
and the Rehabilitation of the Old Town of Mostar,
26-28 October 2000.

 

1.      The ICE endorses the revised plan of operations for the project presented by the PCU and expresses its satisfaction at the implementation of ongoing activities by the PCU.

2.      The ICE asks the PCU to assure timely and appropriate information for assignments, including towards embassies in Bosnia and Herzegovina, who will be asked to publicize the assignments in their countries in order to reach a reasonable number of companies.

3.      The ICE reiterates the decision of the 4th Session regarding the drainage system on both riverbanks behind the abutment walls and also regarding archaeological investigations in the project for the restoration of the two towers. 

4.      The proposals of the joint-venture Yeralti Armacilik-CONEX regarding the reinforcement of the foundations of the Old Bridge and the consolidation of soil behind the abutments are adopted and the joint-venture is asked to correct its final report, which will become the basis for the tender documentation. 

5.      The future contractor for the foundations will be asked to ensure that no ecologically damaging materials or processes will be used, and he will be held responsible for any damage to the environment.

6.      LGA is asked to propose only INOX steel for interior dowels and clamps for the Old Bridge, and  forged iron for visible clamps and the fence that is as similar as possible to the original materials.

7.      The ICE notes that, according to the laboratory tests the stone from Mukosa quarry has the same characteristics as the old tenelija stone used in the Old Bridge.  Therefore, the ICE recommends, after using the maximum quantity of old stone in zones of lower tension, that the tenelija stone from the Mukosa quarry should be used on a regular basis according to the specifications established by General Engineering. 

8.      The ICE expresses concern about the suggestions made by LGA concerning new mortar.  The ICE asks LGA to carry out more complete analysis and investigation of the old mortars in order to prepare the composition of new mortars that will satisfy all archaeological requirements.  It must be known if the composition of the old mortars is acceptable from the viewpoints of statics and durability.   The origin of the colour of red mortar must be clarified, i.e. whether made of bauxite, ground brick, or natural red earth (terra rossa, pouzzalana).   The composition of the new mortars must be submitted to the PCU and UNESCO as soon as possible in order to avoid any delay in the implementation of the plan of operations. 

9.      The ICE suggests that the large blocks of stone still in the Neretva riverbed, which cannot be reused in the restoration process, should remain in their present location in the Neretva riverbed as a testimony and monument to the destruction of the Old Bridge.   At the same time it is suggested that a small significant selection of blocks located on the platform, and of archaeological interest, should be preserved in view of museum display.

10.  The ICE asks General Engineering to prepare proposals for the repair/restoration of the abutment walls against future floods.  The ICE insists that rebuilding the Old Bridge does not imply the repair of small damage: a proper balance must be found between static security, durability and visual effect. 

11.  Regarding the pavement of the Old Bridge it was decided that all the old krecnjak stone should be reused and that the remaining parts should be composed of suitably prepared krecnjak stone in order to attain the same appearance.

12.  The ICE welcomes again the adoption, on 12 June 2000 by the City of Mostar of the Rehabilitation Plan, prepared by UNESCO in 1997.  Nevertheless it deeply regrets that a management plan based on the UNESCO plan has still not been prepared for adoption by the City of Mostar, which unfortunately has facilitated uncontrolled urban development.

13.  The ICE stresses that conservation in Mostar cannot be divided according to municipal districts and recalls to the City of Mostar the urgent necessity of preserving the architectural, historical and environmental values of Mostar as a whole, particularly in connection with the project for the Old Bridge and the nomination for the World Heritage List.   To this effect Messers Beschaouch and Pressouryre are requested to prepare a letter for the signature of the Director-General of UNESCO addressed to the authorities of the City of Mostar.

14.  The ICE welcomes the recommendation of the PCU that the ICE should  reinforce the technical expertise of the evaluation committee for all future assignments. 

 

Next meeting – last week of January or first week of February 2001.