| 5th session of the international commitiee of exports | |
|
5TH SESSION OF THE INTERNATIONAL COMMITIEE OF EXPERTS MOSTAR 26, 27, 28 OCTOBER 2000.
AGENDA Thursday
26. October 2000, 10.00-11.15
Opening of the session, presentation and adoption of the agenda of 11.15-12.30
Presentation of the progress of the works and discussion ( Dr. Colin 12.30-14.00
Lunch 14.00-16.30
Presentation[1]
of the draft final report on Geological investigations
prepared by Joint
Venture CONEX-Yeralti Aramacilik 16.30-18.00
Discussion by ICE and adoption of the proposed project for
strengthening of the foundation, or additional discussion with the
contractor for better clarification of the project. 20.30
Official dinner organised by Mr. Colin Kaiser, UNESCO
Representative in B&H and Professor Leon Pressouyre, The chairman of
the ICE. (Hotel “ERO”). Friday,
27. October 2000 09.30-11.30
Presentation[2]
by LGA company, responsible for Laboratory tests on stone, mortar, lead
and iron 11.30-13.00 Discussion by ICE and adoption of
decisions 13.00-14.30
Lunch 14.30-16.30
Presentation by General Engineering[3]
- Design, Photogrametry and 16.30-18.00
Discussion by ICE and adoption of the decisions or remarks related
to the preliminary design of the Old Bridge. Only after agreement on phase
A will General Engineering be able to begin with the Phase B of their
assignment. 20.30
Official dinner organised by the Project Coordination Unit ‘ PCU Saturday, 28. October 200010.00-11.30
Discussion on the reuse of the old stone, based on the
presentations made by the LGA and General Engineering[4]. 11.30-13.0
a) Discussion on the process of selection and pre-qualification of the contractors to 13.00-14.30
Lunch 14.30-16.00 Preparation of the decisions and
conclusions of the 5th session [1]
After the presentation the contractor (CONEX-YERALTY ARMACILIK)will
leave the meeting room and wait for the eventual second call in order
to clarify some of the questions raised by the members of the ICE .
The Contractor’s team could not consist of more then three persons. 2
After the presentation the contractor (LGA) will leave the meeting
room and wait for the eventual second call in order to clarify some of
the questions raised by the members of the ICE . The Contractor’s
team could not consist of more then three persons. [3]
After the presentation the contractor (General Engineering) will leave
the meeting room and wait for the eventual second call in order to
clarify some of the questions raised by the members of the ICE . The
Contractor’s team could not consist
of more then three persons. [4] The above mentioned companies are requested to be present in Mostar on 28 October, in order to respond to possible additional questions and requirements related to reuse of the old stone and other old materials. |
|
|
Decisions
of the 5th Session of the International Committee
1.
The ICE endorses the revised plan of operations for the project
presented by the PCU and expresses its satisfaction at the implementation of
ongoing activities by the PCU. 2.
The ICE asks the PCU to assure timely and appropriate information for
assignments, including towards embassies in Bosnia and Herzegovina, who will
be asked to publicize the assignments in their countries in order to reach a
reasonable number of companies. 3.
The ICE reiterates the decision of the 4th Session
regarding the drainage system on both riverbanks behind the abutment walls
and also regarding archaeological investigations in the project for the
restoration of the two towers. 4.
The proposals of the joint-venture Yeralti Armacilik-CONEX regarding
the reinforcement of the foundations of the Old Bridge and the consolidation
of soil behind the abutments are adopted and the joint-venture is asked to
correct its final report, which will become the basis for the tender
documentation. 5.
The future contractor for the foundations will be asked to ensure
that no ecologically damaging materials or processes will be used, and he
will be held responsible for any damage to the environment. 6.
LGA is asked to propose only INOX steel for interior dowels and
clamps for the Old Bridge, and forged
iron for visible clamps and the fence that is as similar as possible to the
original materials. 7.
The ICE notes that, according to the laboratory tests the stone from
Mukosa quarry has the same characteristics as the old tenelija stone used in
the Old Bridge. Therefore, the
ICE recommends, after using the maximum quantity of old stone in zones of
lower tension, that the tenelija stone from the Mukosa quarry should be used
on a regular basis according to the specifications established by General
Engineering. 8.
The ICE expresses concern about the suggestions made by LGA
concerning new mortar. The ICE
asks LGA to carry out more complete analysis and investigation of the old
mortars in order to prepare the composition of new mortars that will satisfy
all archaeological requirements. It
must be known if the composition of the old mortars is acceptable from the
viewpoints of statics and durability.
The origin of the colour of red mortar must be clarified, i.e.
whether made of bauxite, ground brick, or natural red earth (terra rossa,
pouzzalana). The
composition of the new mortars must be submitted to the PCU and UNESCO as
soon as possible in order to avoid any delay in the implementation of the
plan of operations. 9.
The ICE suggests that the large blocks of stone still in the Neretva
riverbed, which cannot be reused in the restoration process, should remain
in their present location in the Neretva riverbed as a testimony and
monument to the destruction of the Old Bridge.
At the same time it is suggested that a small significant selection
of blocks located on the platform, and of archaeological interest, should be
preserved in view of museum display. 10.
The ICE asks General Engineering to prepare proposals for the
repair/restoration of the abutment walls against future floods.
The ICE insists that rebuilding the Old Bridge does not imply the
repair of small damage: a proper balance must be found between static
security, durability and visual effect.
11.
Regarding the pavement of the Old Bridge it was decided that all the
old krecnjak stone should be reused and that the remaining parts should be
composed of suitably prepared krecnjak stone in order to attain the same
appearance. 12.
The ICE welcomes again the adoption, on 12 June 2000 by the City of
Mostar of the Rehabilitation Plan, prepared by UNESCO in 1997. Nevertheless it deeply regrets that a management plan based
on the UNESCO plan has still not been prepared for adoption by the City of
Mostar, which unfortunately has facilitated uncontrolled urban development. 13.
The ICE stresses that conservation in Mostar cannot be divided
according to municipal districts and recalls to the City of Mostar the
urgent necessity of preserving the architectural, historical and
environmental values of Mostar as a whole, particularly in connection with
the project for the Old Bridge and the nomination for the World Heritage
List. To this effect
Messers Beschaouch and Pressouryre are requested to prepare a letter for the
signature of the Director-General of UNESCO addressed to the authorities of
the City of Mostar. 14.
The ICE welcomes the recommendation of the PCU that the ICE should
reinforce the technical expertise of the evaluation committee for all
future assignments.
Next
meeting – last week of January or first week of February 2001.
|
|