Procurement
Project Coordination Unit was with the decision of the
City Administration of Mostar (numbered 01-1768/98), as the borrower,
established on 1st December 1999. Approval for the appointment of
the procurement officer the Bank gave on 23rd December 1999. Till
the establishment of the Project Coordination Unit, the Old Bridge project had
been handled by the "Stari Mostar" Foundation. The operation of the
Project Coordination Unit in a way represents a continuity of the assignment
with the ultimate goal of the Old Bridge restoration, namely the cultural
heritage of the city in a wider perspective. So as for procurement we shall
summarize the activities of the Foundation, which have been covered in its
report on the occasion of its cease of operation and which has been presented
both to the Project Coordination Unit and to the public as well.
It deals with the following procurements of the goods and
works:
●
Purchase
of the tenelija stone and its transport and the duly storage;
●
Furnishing
of the Project Coordination Unit, namely:
a.
Rent and
adaptation of the premises
b.
Purchase
of a car
c.
Purchase
of computers (2 pieces)
d.
Purchase
of the office furniture
e.
Telephone
lines and the Internet connection
For the abovementioned purchases Project Coordination Unit raised
the question of retroactive financing with the World Bank. As far as procuring
activities of the Project Coordination Unit in 1999. are concerned, it can be
divided into two basic groups, namely:
●
National
shopping
●
Procurement
of the consultant services by way of International Competitive Bidding (IJN-ICB)
Procurement of the goods according to the national
shopping principles has been applied to the following concrete goods:
Computers for the employees in the Project Coordination
Unit (6 pieces) and the accompanying equipment, which has been amended with the
UPS units
Office material and petty office equipment (coffee-making
machine, a calculator, refrigerator, vacuum-cleaner)
Indispensable payments for the services of post office,
electric energy bills, fuel bills.
For the abovementioned procurement Project Coordination
Unit has followed a sound public customer practice and it was completely
approved by the World Bank.
As to this procurement, it was described in detail in
tables which make up this report. Here it deals with particular activities
planned in the Bank procedures, which have been approved by the Bank, and which
are indispensable for certain works to be accomplished in the best way possible
for the Project. The report covers the following procurements of the works:
1.
Geological
investigations, surveying of the abutments and pathological analysis
2.
Cutting
of the tenelija stone which has been stored at “Komos” city dump
3.
Design,
photogrametry and calculations for the Old Bridge in Mostar
4.
Identification
on ancient construction materials and determination of new construction
materials for the Old Bridge
5.
Design,
reconstruction of the towers Tara and Halebija
|
Procurement implementation inclusive 30.06.2000 -
architect |
||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
Description |
Cost estimate |
Tender no. |
Sources of funds |
Procurement method |
Bid invitation |
Bid submission |
Bid evaluation |
Contract signature |
|
|
|
Selection of architect for towers
Tara and Halebija |
200 000 US$ |
6 |
Dutch Grant |
ICB-QCBS |
Scheduled to take place at the end
of August; |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
World
Bank has not adopted the proposal for the short list of consultants put forth
by the PCU in the document dated 13.04.2000. PCU has set up the short list
comprising only the the local companies and that is why It has not been
approved by the Unesco and the World Bank. |
|
|||||||||
|
Invitation
for expression of interest was published on 14.06.2000 in Development
Business and in the local newspapers of "Dnevni Avaz" and
"Slobodna Dalmacija". |
|
|||||||||
|
The
bidding documentation is harmonized with the World Bank. |
|
|||||||||
|
Procurement implementation inclusive 30.06.2000. - cutting
of the stone |
||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
Description |
Cost estimate |
Tender no. |
Sources of funds |
Procurement method |
Bidding invitation |
Bid submission |
Bid estimate |
Potpis ugovora |
Contract signature |
|
|
Cutting of the tenelija stone
stored in "Komos" city dump |
130 000 US$ |
|
Italian Grant funds under IDA |
NCB |
Not limited; we expect bidding
invitations around 20.-25.08.2000. |
Scheduled between 20.-25.09.2000. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Part
of the stone quantity amounting 400 m3 of the commercial stone was
procured by "Stari Mostar" Foundation and the stone was duly
deposited in the appropriate storage. As the World Bank has not planned the
financing from the IDA of this procurement, and the need was ascertained for
the quantity bigger than the quoted one, in consultation with the World Bank
we seek the best way to implement this specific procurement relating to one historical
source and the limited quantity of the remaining supplies. |
||||||||||
|
Procurement implementation inclusive 30.06.2000 - design |
||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
Description |
Cost estimate |
Tender no. |
Sources of funds |
Procurement method |
Bidding invitation |
Bid submission |
Bid evaluation |
Contract signature |
|
|
|
Design, photogrammetry, and
calculations of the Old Bridge |
195 000 USD |
3 |
Means administered by donors |
LIB - Fixed Budget Selection |
07.12.1999. |
24.01.2000. |
09.03.2000. |
24.04.2000. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Estimate
of the signed contract is 195 000 US$. |
|
|||||||||
|
Procurement implementation inclusive 30.06.2000. -
laboratory tests |
||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
Description |
Cost estimate |
Tender no. |
Sources of funds |
Procurement method |
Bid invitation |
Podnošenje ponude |
Bid evaluation |
Contract signature |
|
|
|
Identification of ancient
construction materials and determination of new construction materials for
the Old Bridge |
40 000 USD |
5 |
IDA |
ICB |
01.02.2000; |
20.03.2000; |
14.04.2000. |
15.06.2000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PCU made the bid assignment for this procurement,
sent it to the Bank for inspection and set up a short list of 6 companies: |
|
|||||||||
|
The
amount of the contract made with the company LGA costs 160.061,00 €. |
|
|||||||||
Procurement implementation inclusive 30.06.2000. - geological investigations |
|||||||||
|
|
|
|
|
|
|
|
|
|
|
|
Description |
Cost estimate |
Tender no. |
Fund sources |
Procurement method |
Bid invitation |
Bid submission |
Bid estimate |
Contract signature |
|
|
Geological investigations, survey (the measurements) of the
retaining stones and the pathological analysis |
400 000 USD |
6 |
IDA (International Development Association) |
LIB (Limited international competition) |
21.07.1999 |
20.09.1999 |
|
11.02.2000. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The short list of companies to which the bidding documents have been sent has been set up the Stari
Mostar Foundation. Pre-bid conference has been held on 5th August 1999. The
bids should have been delivered up to 24th August, but that deadline has been
delayed two times, once at the request of the director and the deputy, and
the second time on the request of the Turkish bidder Yeralti Aramacilik.
After establisment of committee in the composition of: |
|||||||||
|
The procurement in question has been contracted in an amount
of 1 308 449 German marks. |
|||||||||