BOSNIA AND HERZEGOVINA                            88 000 Mostar, Adema Buća 17

BiH FEDERATION                                                 Phone no.++ 387 36 550 805/550 806

CITY OF MOSTAR                                                    Telefax no. ++ 387 36 550 804

PCU                                                                                   E-mail – pcu@starimost.ba

 

Number 02 07 844

Mostar, 1st July 2002

 

World Bank

Infrastructure Sector Unit

Regional Office for Europe and Central Asia

 

 

 

 

Report on the project status of the

“Old Bridge” in Mostar

Bosnia and Herzegovina

in the period from 1st January 2002 to 30th June 2002

 

 

 

Yours sincerely,

 

 

 

PCU – Deputy director                                                PCU – Director

 

      Tihomir Rozić                                                            Rusmir Čišić

          (signed)                                                                      (signed)

 


Contents:

 

1.       Activities on the project in the abovementioned period

2.       Neighborhood component

3.       Technical activities in the project in the abovementioned period

4.       Financial report

 


Activities in the project in the period from 1st January 2002 to 30th June 2002

Works in the first six months of 2002 have necessitated big efforts by the Project Coordination Unit in the realization of all the set assignments. The plan of activity for the past period has run in the following order:

 

1.       Completion of the works at the foundations of the bridge

2.       Completion of the works in the archaeological excavations of the towers and the structures between the towers – the bridge

3.       Testing of the underground waters below the towers

4.       Completion of the project documentation for the towers ““Tara””, ““Halebija”” and the structures among the towers – the bridge

5.       Announcement of the pre-qualifications for the building of the towers

6.       Selection of the company for the building of the bridge

7.       Selection of the company for the supervisor at the building of the bridge

8.       Stone block cutting operation for the bridge

9.       Completion of the neighbourhood component 4,5

10.   Implementation of the tender, and the selection of the company for the structure numbered 6.

11.   Preparation of the project documentation for the structure of the Croatian Cultural Association “Napredak” (from the program “Structures belonging to three different peoples”)

12.   Program of“UNESCO” – Kriva ćuprija

 

1)     Completion of the works at the foundations of the bridge

The Old Bridge foundation repair was implemented by the Turkish company Yapi Merkezi.

Contract numbered 001/2002 was signed on 26th April 2001.

In accordance with the contract the works were to be completed on 30th October 2001.

Owing to the changes in the project, and the additional requirements by the UNESCO, the works were extended till 1st February 2002.

The Project Coordination Unit met all the necessary requirements by the experts of UNESCO, aware that the quality of the works constitutes the primary interest of all the participants in the project.

Project Coordination Unit engaged a special company which has implemented the underwater survey of the foundations of the bridge. With the survey of the photographic documentation you may draw a conclusion that the repair of the foundations was carried out successfully and conforming to high-quality standards.

A special emphasis was made to take care of the environmental aspect.

In the final cleaning of the Neretva riverbed, at the locality of the Old Bridge, Yapi Merkezi has carried out the complete cleaning of the riverbed, removing every item, anchor, tube, bar, and so forth.

When the works on the bridge foundation repair were finished, Project Coordination Unit set up a committee for the technical delivery of the works:

 

The committee was composed of:

 

    1.   Mr. Gilles Péqueux – Supervision Leader

    2.   Ms. Snježana Hadžić – Supervising Engineer

    3.   Prof. Mr. Tomislav Ivanković - Supervising Engineer

    4.   Mr. Tihomir Rozić – Project Coordination Unit

    5.   Mr. Rusmir Čišić – Project Coordination Unit

    6.   Mr. Ferhat Mulabegović – expert of UNESCO

    7.   Prof. Mr. Zlatko Langof - expert of UNESCO

    8.   Mr. Léon Pressoyre – UNESCO Expert Team Leader

    9.   Mr. Mehmed Oguz – Director of the Project Yapi Merkezi

 10.   Mr. Gökhan Günal – Site Foreman (“Yapi Merkezi”)

 

The committee set out to check the comprehensive documentation in detail, and then it has taken into consideration as well the video footage of the underground survey of the foundations of the bridge.

The committee stated that the comprehensive documentation has been prepared thoroughly and well.

Then a site tour followed, where we on the very spot stated that the works have been executed well and successfully.

According to the order of the Project Coordination Unit Yapi Merkezi company has left the šipove[DP1]  for the future façade scaffolding which will be used for the repair of the bank walls.

In the Technical assistance has been prepared the minutes on the technical delivery, which has been signed by the Project Coordination Unit, supervision of the works, contractor. The experts of UNESCO have not signed the abovementioned minutes.

Representatives of UNESCO deem that UNESCO is the expert consultant in the project, and that they are not the signatories of the minutes of the technical delivery of the foundations of the Old Bridge.

The Project Coordination Unit has accepted the explanation of Mr. Pressoyre, and in such a way brought the operation of the Old Bridge foundation repair to its end.

 

2)     Archaeological works at the “Tara” and “Halebija” and the adjacent structures between the bridge and the towers

On 27th December 2001 NCB 006/2001 contract was signed, called “Works necessary for the archaeological investigations at the locality of “Tara” and “Halebija” towers by the Old Bridge in Mostar”.

The contract was signed with the “Grasa” company from Zagreb.

With the archaeological works the designer Omega Engineering has received the answers to many questions, which have been previously unresolved while preparing the project documentation for the abovementioned structures. The works on the archaeological excavations were ended by the end of February 2002.

The archaeological study was completed by the Omega Engineering company.

The supervision on the works was implemented by Mr. Tihomir Rozić (Project Coordination Unit Mostar).

The complete documentation was submitted to revision on 10th June 2002 to UNESCO in Sarajevo.

 

3)     Contract numbered CCS 06/2002

The complete subject covers:

              1.   The monitoring of the underground waters of the Neretva river and the walls of the Old Bridge in Mostar

              2.   Testing of the underground waters in the area of the Old Bridge and the “Tara” and “Halebija” towers

              3.   Geotechnical conditions of the foundations of the “Tara” and “Halebija” towers

 

During repair of the foundations of the Old Bridge in Mostar, monitoring has been installed, containing 3 (three) piezometers on the right hand side, one piezometer on the left side and one inclinometer and one extensiometer respectively in the walls of the bridge at each side. With this monitoring are continually recorded the oscillations of the underground water level and the Neretva river as well and the displacement of the walls too and the ground rock of the Old Bridge.

All the measuring data are stored in the central memory of the data logger in the digital form. All the measurements are taken automatically and simultaneously with the option of adjusting the intervals of the measurement from 1 to 999 minutes.

For the period till the start of the building of the arch, it is recommended to have the measurement interval of 15’.

With the point one (1) is covered:

 

·        measurement, maintenance, calibrating and repair of the monitoring system

·        data processing

·        data interpretation

·        outstanding interpretations

·        final interpretation

 

Testing of the underground water is considered to be a very important assignment. In the documentation on the accomplished investigation works, which were prepared by the “Yeralti Aramacilik” and “Conex” there are indications of existence of a vodonosni horizont[DP2]  at the points which correspond to the zones of the ground rock of the towers at the right riverbank and the upper part of the wall filling.

As well it was predicted to pour minor quantities of the underground water marker (Na – fluorescene), to take the water samples and to carry out the laboratory tests of the presence of the marker in the samples.

The results of the abovementioned works and the interpretation of the results of the monitoring will enable the definition of the influence of the underground water to the “Tara” and “Halebija” towers and to the walls of the Old Bridge. Regarding that point, the most appropriate locations for the preparation of the horizontal drainage will be determined.

Geotechnical conditions of the foundations of the “Tara” and “Halebija” towers

Data on evaluation of the geotechnical conditions of the Tara” and “Halebija” tower foundations are found in the documentation of the investigation works for the Old Bridge. and the implementation documentation of the repair of the Old Bridge foundations.

Holes which have been excavated in the archaeological investigations will be used for the thorough geotechnical surveys with the geotechnical classification and no less than 10 soil samples for the laboratory tests will be taken.

The prepared masterplan will contain all the relevant analyses, calculations, graphic attachments, based on which the competent evaluation of the geotechnical conditions of the “Tara” and “Halebija” tower founding will be made.

 

4)     Completion of the project documentation for the "Tara" and "Halebija" towers and the structures among the bridge - towers

At the very beginning of the project documentation preparation, Omega Engineering requested to set down to archaeological investigations urgently.

Technical assistance was not prompt in that moment, but the archaeological problem was tackled as late as 30th August 2001 when Project Coordination Unit strongly requested from the Technical assistance to prepare an assignment for the archaeological investigations. Project Coordination Unit immediately launched a tender for the works relating to archaeological investigations.

“Grasa” company was awarded the realization of the works in the field of archaeology, and the Omega Engineering company put down a detailed archaeological study, which accelerated the completion of the comprehensive tower project.

On 26th June 2002 Omega Engineering submitted the whole project to the revision of UNESCO. With the completion of revision of the project, Omega Engineering company will submit the documentation for the tender of building towers.

With it the first part of the contract is over, whereas the other part of the contract consists of supervision on the building of the towers and the structures by the towers and the bridge.

Supervision is accomplished as well by the Omega Engineering company (preparation of the contract).

 

5)     Announcement of the pre-qualifications for the building of the "Tara" and "Halebija" towers and the structures for the towers and the bridge.

Since the World Bank approved the advertisement announcement, Project Coordination Unit published the announcement in the local newspapers: “Avaz” and “Večernji list”.

World Bank published the advertisement in the Development Business.

In the advertisements were defined and provided all the necessary information. The submission of documents was planned to take place on 5th July 2002, but due to the short deadline the participating companies asked for an extension till 12th July 2002. As World Bank approved the extension, the deadline was postponed to 12th July 2002 till 2 p.m.

UNESCO appointed its expert who is going to participate in the tender committee as well.

 

6)     Selection of the companies for the building of the bridge

In the pre-qualification process of the companies for the building of the bridge, it is familiar that out of eight registered companies three companies were approved:

 

    1.   ER-BU – from Turkey

    2.   Quelin – from France

    3.   Pontello – “Hidrogradnja” a joint venture (Italy – Bosnia and Herzegovina)

 

On 12th February 2002 the opening of the submitted bids by the abovementioned companies took place. Analyzing the abovementioned bids, the tender committee stated that the most favourable bid belonged to Turkish company ER-BU, and that the bid amounted 2.105.000, 00 USD.

On 15th February 2002 World Bank sent its approval, thus confirming that the building of the Old Bridge in Mostar was to be entrusted with ER-BU company. Project Coordination Unit duly informed the company on the job awarded.

ER-BU company sent on 10th March 2002 its first crew which started the first preparations.

Completion, the ceremony of signing of the contract, Project Coordination Unit on 19th April 2002 sent to the ER-BU company a letter of proposal, where it suggested the preparation of the necessary documentation:

 

    1.   Site organization project

    2.   Site security project

    3.   Work protection project

    4.   Crane path project, assembly of the crane

    5.   Frontage scaffolding project

    6.   Centering project

    7.   Timeframe of the works

    8.   Quality control plan

    9.   Implementation project

 10.   Environmental project

 

ER-BU accepted the proposal of the Project Coordination Unit, and it set down to the preparation of the abovementioned documentation.

With the selection of the supervisor, the abovementioned documentation was ready to be checked by the supervisor, and to be approved for realization of the individual parts.

Project Coordination Unit as well set down to prepare the contract, in order to sign it with the Turkish company ER-BU as soon as possible.

The formal ceremony of signing the contract was effectuated on 17th April 2002.

This historical act was accomplished in the presence of a large number of invitees. In addition to the representatives of the World Bank, UNESCO, Aga Khan, the ceremony was attended by a high number of ambassadors accredited in Bosnia and Herzegovina and the representatives of the authorities of the state of Bosnia and Herzegovina and Bosnia and Herzegovina Federation.

As well we have to stress that the abovementioned gathering was attended by the representatives of the donor countries as well.

At this formal ceremony the Ambassador of Republic of Croatia, formally handed in the donation of his country, for the building of the bridge, amounting 500.000 USD.

This moment was specially welcomed.

In his speech Ambassador of Republic of Croatia highlighted the great importance of the building of the bridge in the creation of friendship between Bosnia and Herzegovina and the Republic of Croatia, and towards establishing extremely good interpersonal relationships in these areas[DP3] .

On 27th June 2002 the City of Mostar was visited by the president of Italy. In the protocol of the visit it was planned to start the chiselling stone operation. The ceremony went in a nice and friendly atmosphere.

We believe that the Turkish company ER-BU grasped the importance of this world-class project, and that it will meet fully the contracted obligations.

 

7)     Selection of the companies for the supervision at the building of the Old Bridge

On 25th April 2001 we announced an advertisement for the expression of interest of the companies for the supervision.

The final date of announcement was 16th May 2001.

For the supervision registered 20 companies, and the tender committee composed of representatives of Project Coordination Unit and UNESCO, appointed a short list of 6 companies:

 

    1.   “Arcoing” – Slovenia – Bosnia and Herzegovina

    2.   “Bonifica” – Italy

    3.   “Enel-Hydro” – Italy

    4.   “BGS-Interprojekt” – Germany – Bosnia and Herzegovina

    5.   “Bill Harvey” – England

    6.   Omega Engineering – Croatia

 

The abovementioned companies were approved by the World Bank for the submission of the technical and financial bid for the abovementioned assignment.

On 7th March 2002 the opening of the four submitted bids took place, namely:

 

    1.   “Arcoing”

    2.   “Bonifica”

    3.   “BGS-Interprojekt”

    4.   Omega Engineering

 

The evaluation of the submitted bids was made by the tender committee in the following composition:

 

    1.   Mr. Léon Pressoyre – UNESCO

    2.   Mr. Azedine Beschaouch – UNESCO

    3.   Mr. Colin Kaiser – UNESCO

    4.   Mr. Zlatko Langof – UNESCO

    5.   Mr. Rusmir Čišić – Project Coordination Unit

    6.   Mr. Tihomir Rozić – Project Coordination Unit

    7.   Mr. Anto Šain – Project Coordination Unit

 

The bid of the “Arcoing” company was evaluated with very low marks, since from their bid the experts from Slovenian institute had been cancelled[DP4] ,  and those experts constituted the real strength of this joint venture.

Owing to the experts of the abovementioned institute in the pre-qualification process, “Arcoing” company managed to be short-listed, and thus met the pre-qualification requirements. Why they wanted to deceive the tender committee, UNESCO, World Bank, it was not clear to us.

The remaining companies received good marks from the Project Coordination Unit, namely its members, whereas the marks of the experts were catastrophic.

Compiling the final report for the World Bank, it could draw a conclusion that in the grand total over 70 points had the “Bonifica” company from Italy, whereas the other companies BGS, Omega Engineering were thrown out of the further competition. Aware that in accordance with the procedures of the World Bank it is not possible to analyze only one company, and to open up only its financial bid, Project Coordination Unit representatives immediately sent a letter to the World Bank, stating that the work of this committee was not regular and successful and required from the World Bank to set up a new independent tender committee. World Bank asked for the comprehensive technical documentation of the companies which had submitted their technical bids.

After a detailed analysis World Bank made a decision to set up an independent tender committee.

As the new members of the tender committee were appointed:

 

Prof. Mr. Amir Pašić – Istanbul, Turkey

Mrs. June Taboroff – United States of America

Mr. Miljenko Domijan – Croatia

 

New tender committee sent its evaluation tables, and provided its comments to the Project Coordination Unit, and the Project Coordination Unit addressed all the documentation to the World Bank.

Approval for the technical evaluation of the abovementioned companies World Bank sent on 1st May 2002.

On 7th May 2002 at 12 o’clock in the premises of the Project Coordination Unit the opening of the financial bids of the abovementioned companies took place.

The prepared report of the technical and the financial bid proveded the following order of the companies:

 

    1.   BGS

    2.   Omega Engineering

    3.   Bonifica

 

On 9th May 2002 World Bank approved the negotiations on contract with the BGS company.

Project Coordination Unit immediately started negotiations and out of eight problematic points very quickly harmonized the first seven points. The last point referred to the engagement of the expert Mrs. Zeynep Ahunbay. While analyzing the technical evaluation of the BGS company, the staff column, Mrs. Zeynep Ahunbay was awarded the highest marks and in such a way enabled the BGS company to participate further in the competition. When the Project Coordination Unit asked for the time of engagement of Mrs. Zeynep Ahunbay in the project, BGS proposed seven (7) days.

Project Coordination Unit could not accept that a member of the key personnel (conservationist, restorator) in the project spends seven working days in a month .

In the beginning of the negotiations Project Coordination Unit asked for Mrs. Zeynep Ahunbay to spend a whole month in the period of 18 months.

Aware of the great occupancy of Mrs. Ahunbay, Project Coordination Unit conceded to 15 working days, in the period of 18 months. BGS was not able to fulfill the required period, and it [DP5]  intended? to fill in the vacant period with Mr. Prof. Kusto.

Project Coordination Unit could not accept the proposed proposal, but it held firm to its principles, not wishing to give way below employment of 15 working days for Mrs. Ahunbay, aware of the difficulty of the project and the total assignment.

Aware of the great responsibility and the difficulty of the project of the building of the Old Bridge, Project Coordination Unit could not make any further concessions below the abovementioned number of days.

BGS at the end of the talks offered 11 (eleven) working days.

After big negotiations, and the correspondence between BGS, Project Coordination Unit and World Bank, Project Coordination Unit requested from World Bank to approve the termination of the negotiations, and to approve the negotiations with the second-ranged company Omega Engineering from Dubrovnik.

On 15th June 2002 World Bank approved Project Coordination Unit to start the negotiations with Omega Engineering. On 19th June 2002 Project Coordination Unit and Omega Engineering company started negotiations.

Project Coordination Unit was categorical in fulfilling all the requirements. Conservationist PhD. Mr. Željko Peković agreed to work for 30 days on the project in the period of 18 months.

As well director of the project Mr. Gotovac B. confirmed his stay for 30 days in the period of 18 months.

And the remaining personnel as well fulfilled all the requirements of the Project Coordination Unit.

On 21st May Project Coordination Unit sent the contract to the World Bank, and it received its approval to the contract on      

On       Project Coordination Unit signed a contract with Omega Engineering, company which will implement the supervision at the building of the Old Bridge in Mostar.

 

8)     Stone cutting operation

On 8th November 2001 Project Coordination Unit signed a new contract with the “Dent – kamen” company from Mostar, relating to the delivery of 300 m3 for the needs of the building of the bridge. Since the advance payment amounting 150.000,00 DEM (50% of the contracted amount) has been duly paid, “Dent – kamen” company set out to prepare the abovementioned stone quantities.

For the past period of six months in 2002 it was delivered 208 m3 of stone, whereas the remaining 92 m3 of stone will be delivered during July and August.

After the realization of the abovementioned contract Project Coordination Unit plans in August 2002 to contract the last 150 m3 of stone, and in such a way to bring the stone procurement to its end. Out of the abovementioned stone quantity, 50 m3 of stone will be used as the spare stone in case of damaging of the cut blocks. Project Coordination Unit will deliver this stone quantity to the ER-BU company as the contractor.

“KARA-DRVO” company from Kiseljak which accomplishes the stone cutting operation, cut 910 blocks with the supervision of the Geological Institute of Bosnia and Herzegovina from Sarajevo. The remaining 170 blocks we would like to realize as soon as possible in order to complete this operation fully, and in such a way to enable to the contractor to start the operation of the chiselling of the stone.

 

9)     Completion of the structures belonging to the neighbourhood component

By the end of 1001 Project Coordination Unit signed two contracts within the neighbourhood component program.

1.       Northeastern zone of the banks of the Radobolja river

2.       Jusovina square - the access to the river

The works were accomplished successfully by the contractor.

Committee for the technical evaluation composed of the representatives of the Project Coordination Unit, duly surveyed the abovementioned structures.

All the remarks which were made on the technical delivery were removed, and in the repeated survey it was found out that the structures were done well and conforming to high-quality standards.

Finishing with these two structures, Project Coordination Unit completed five (5) structures out of the complete eleven (11) structures belonging to the neighbourhood component.

 

10)Implementation of tender for the selection of the companies for the structure 5.

As Project Coordination Unit received the approval from the World Bank to launch the tender for the structure “General improvement of the banks of Radobolja between the bridges of Kriva ćuprija and Oručevića m.”, that was done on 14th June 2002.

At the tender the following companies turned up:

1.       Hidrogradnja SARAJEVO......................................................................... 98.681,00 KM

2.       “MAČ” Mostar ........................................................................................ 191.290,00 KM

3.       “Fajić” construction company Mostar ........................................................ 64.540,00 KM

4.       “Garant” Mostar........................................................................................ 85.335,00 KM

5.       “Bišina” Mostar ........................................................................................ 89.775,00 KM

After the analysis of the submitted bids the tender committee concluded that the bid of the “Fajić” construction company was the most favourable one, and that it amounts 64.540,00 KM.

In the expectation of the approval from the World Ban Project Coordination Unit prepares a contract for the abovementioned company, in order for the works to start as soon as possible.

 

11)Preparation of the project documentation for the structure of “Napredak” Croatian Cultural Association (from the program encompassing three structures to three peoples)

As you are aware, the program of the rehabilitation of the structures belonging to three peoples is still under way.

The project documentation for the rehabilitation of the buildings of the “Napredak” Croatian Cultural Association belonging to the Croatian peoples has been prepared.

By finishing the structural engineering of the structure, and its installation, Project Coordination Unit will launch a tender for the implementation of the works by the end of September 2002.

After contractual signature with the future contractor of the works, follows the completion of the project documentation for the Wakuf Palace and the Metropolitan Palace.

The project documentation for the abovementioned structures will be prepared by the designing office of the Aga Khan Foundation in Mostar.

 

12)Program of “UNESCO”

Program of “UNESCO” covers the building of the Kriva cuprija in Mostar.

As you are aware the means for this project have been provided by the government of Luxembourg. UNESCO has prepared the project documentation, it has launched the tender and carried out the selection of the contractors. “Garant” company from Mostar has accomplished the abovementioned structure exceptionally well and respecting high-quality standards.

Soon it is expected to start the building of the traditional Turkish city baths called “Hamam”, where UNESCO runs the whole program of the works as well.

The refurbishment of the structures in the old city part with each day takes a nice look both in the eyes of tourists, and all the citizens of the city of Mostar.

Final comments and the problematic points of the Project Coordination Unit

At the end of this report we would like to voice some negative remarks in the course of the work in the project.

A big shortcoming of the technical assistance we deem to be the archaeological investigation of the towers. We opine that the technical assistance should place the archaeological investigations in the project assignment of the preparation of the main design of the “Tara” and “Halebija” towers. In this case the companies would provide the complete bid as well for the complete assignment. The additional preparation of the assignment for the archaeological investigations, implementation of the tender for the archaeological works, has brought about a delay lasting six months, so that the Omega Engineering company faced a very difficult situation.

Only with a great engagement the abovementioned company the preparation of the main design was brought to its end.

We have to stress as well that the project documentation preparation for the building of the bridge, implementation of the tender for the building of the bridge, has taken a long time too.

The standpoints of the technical assistance and UNESCO were extremely firm, in particular while selecting the companies to build the bridge.

The selection of the supervisor specially slowed down the work on the building of the bridge. The tender committee composed of the representatives of the Project Coordination Unit and UNESCO, did not yield the expected results.

As you are aware, the expert team of UNESCO which was engaged in the tender committee headed by Mr. Pressoyre, did not provide the passing marks to the companies of BGS and Omega Engineering, but only to Bonifica.

Since in compliance with the World Bank procedures it is not possible, World Bank set up a new committee comprising three independent members who realistically analyzed the technical bids, and they provided their approval to the three companies: BGS, Omega Engineering and Bonifica.

At the opening of the financial bids the order of the companies for the supervision looked as follows:

1.       BGS

2.       Omega Engineering

3.       Bonifica

Since we set down to negotiations for the signature of the contract with the BGS company, big problems emerged with regard to the engagement of Mrs. Zeynep Ahunbay, whom BGS was not able to include more than 11 days a month, and Project Coordination Unit could not accept it.

These negotiations and the correspondence lasted over 40 days. When all the options were tried out, Project Coordination Unit demanded from the World Bank to allow for negotiations with the second-ranged company to be held.

As you can conclude, the process of the supervisor selection lasted for a long time too.

We are all aware that the expert conference was held on 6th April 2001.

The abovementioned expert conference was chaired by Mr. Léon Pressoyre.

Since the date of the holding of the abovementioned conference, the interest of the experts of UNESCO, excepting the office in Sarajevo, in the project of the Old Bridge in Mostar faded quickly.

About those problems we notified Mr. Bouchenaki too during his visit on 27th June 2002 in Mostar when he visited Project Coordination Unit.

Project Coordination Unit overcame all the problems in the past period, and it overcame with the World Bank.

Owing to the World Bank, Project Coordination Unit realized successfully, and brought the project in a fairly good state.

Project Coordination Unit wants to point out as well that without joint work of the World Bank, technical assistance, UNESCO, Aga Khan, city administration of the city of Mostar the normal realization of the complete project will not be possible.

Mr. Bouchenaki expressed his readiness to hold a conference of experts in September, where he himself would chair the conference.

Public relations, marketing of the project, still remains the Achilles’ heel of the project.

Mr. Drnda Adnan, who received approval from the World Bank, has not turned up yet at the negotiations with the Project Coordination Unit.

Project Coordination Unit on two occasions asked for a meeting with a view to further negotiations, and the contractual preparation.

If Mr. Drnda does not show up in the next period, Project Coordination Unit will ask for the further instructions from the World Bank for the solution of the abovementioned problem.

As well we would like to underline a good collaboration with the city administration of the city of Mostar and the cooperation with Aga Khan Foundation which as well invests big efforts in the realization, and the restoration of the neighbourhood component structures.

Finally, we would like to extend our warmest thanks to Mr. Lawrence Hannah, Mr. Ahmet Gokce, Mr. Joseph Ingram, and to Mrs. Vesna Frančić who invest great efforts in the realization of the project of the Old Bridge in Mostar.


 [DP1] ne znam

 [DP2] ne znam

 [DP3] Da li ovdje nedostaje jedna stranica?

 [DP4] ne znam pročitati!

 [DP5] ne znam pročitati!