BOSNIA AND HERZEGOVINA 88 000 Mostar, Adema Buća 17
Mostar, 10.01.02.
Infrastructure
Sector unit
Regional
office for Europe and central Asia
Report on the status of the
project
“Old Bridge” in Mostar
Bosnia and Herzegovina
Period covering 30.06.2001 –
31.12.2001.
PCU – Deputy director
PCU – Director
Tihomir Rozić
Rusmir Čišić
(signed)
(signed)
Contents:
1.
Activities in the project covering the abovementioned period
2.
Neighbourhood component
3.
Technical activities on the project in the past period
4.
Financial report
Activities in the project
covering the abovementioned period
In the early 2001. god. PCU has prepared an extremely ambitious
plan of activities in 2001.
(I)
The first contract which has been signed on 27.01.2001. god. has
dealt with the preparation of the main project of the repair of the «Tara and
Halebija» towers, as well as the structures located between the towers and the
Old Bridge.
(II)
The second contract deals with the start of the works with
regard to Old Bridge foundation repair. The abovementioned contract has been
signed on 26.04.2001. god.
(III)
As the first stone cutting phase has been finalized, PCU in consultation with the city
administration of the city of Mostar on 08.05.2001., a contract pertaining the
acquisition of 200m3 of stone has been signed. As well has been
signed the contract relating to the stone extraction supervision from «Mukoša»
quarry, and the supervision on the cutting of the remaining stone quantities
too.
(IV)
Pre-qualification of the companies for building of the bridge
has been completed.
(V)
Pre-qualification of the companies for the supervisor for the
building of the bridge has been completed.
In our further exposition we wish to cover every single item in
detail, and to provide you with the best information for any position.
I Contract numbered 004/2001 – «Tara and Halebija» tower reconstruction
In our report presenting
activities from 01.01.2001. to 30.06.2001. we have described in detail the
course of activities at this assignment. At the very beginning of the
realization of the set assignment, Omega Engineering company pointed out on
22.02.200. the problems with archaeological investigations. Tehnical
Assistance, Mr Gilles Pequeux has not duly reacted to the assignment set by
Omega Engineering. The comprehensive problem archaeology has been discussed at
the technical meeting which has been held on 30.08.2001. at the initiative
of Mr. Rozić Tihomir (PCU – Mostar). At
the abovementioned meeting the minutes of Mr.. Nicolas Fachere has been
accepted for Omega Engineering to carry out the archaeological investigations, and that their assignment should
be enlarged to comprise Herceguša tower as well. The assignment extension will
be split into three parts:
(A) Appendix of the
contract of the consultant within the points to authorize by procuedure
(B) Construction works
which have to be implemented regarding the archaeological investigations
(C)
Study of the drainage works
All the activities under the
point (A) have been undertaken by Omega Engineering. Under point (B) PCU has
implemented a tender for the archaeological investigations. Tender was carried
out on 19.10.2001. where the following companies have shown up:
1.
Hidrogradnja – Sarajevo
2.
Grasa – Zagreb
3.
Dom-Izgradnja – Dubrovnik
After the bid opening, and the
detailed analysis of the bids, tender committee has confirmed that the company
GRASA from Zagreb has been the most detailed one and the one conforming to the
highest quality standards, so that the tender committee has opted for the
abovementioned company. On 11.12.2001. we received the approval for the
abovementioned company. PCU Mostar on 21.12.2001. signed a contract for the
abovementioned company, with work completion deadline 90 days. The preparation
of the main project for the towers, Omega Engineering plans to finish on
30.03.2002.. It has been decided that the study of the water regime and the
drainage for the walls should be restored later on. Cost estimate of the repair
of the towers and the structures between the bridge and the towers amount 1.7
million $. PCU prepares advertisement for the prequalification of the companies
for the building of the towers and the structures. The advertisement was sent
to the World Bank on 15.01.2002., so we expect its approval soon. The procedure
of the pre-qualification of the companies we wish to carry out in order to
accomplish the comprehensive tender as soon as possible, and to enable the
start of the building of the towers and the structures.
II Contract numbered 001/2001 regarding bridge
foundation repair
As you know Old Bridge
foundation repair contract was signed with the Yapi Merkezi company from
Istanbul on 26.04.2001. The preliminary works lasted till 07.06.2001. when the start of the works has
officially taken place. The supervision team has been led by Mr. Gilles
Pequeux, consisting of Ms. Snježana Hadžić and prof. Tomislav Ivanković. At the
very beginning of the works certain project changes have taken place. It has
been decided that instead of DURABAG BAGS we should implement a classical board
formwork of the (9) selections on the right foundation, and then to grout them.
As the supervision has completely accepted the abovementioned changes Yapi
Merkezi set out to implement the assignment mentioned above. We have to point
out that the works in June, July, August and Septembru were implemented very
slowly, not sticking to the timeframe. PCU has invested the best efforts to
ensure the appropriate water level in order for Yapi Merkezi to realize its
assignment unimpededly. We would like to point out a big engagement of the EP
BiH and EP HZHB who have made big efforts in order to enable the appropriate
water level during the works. In October a considerable acceleration of the
works has taken place, taking into account that the climatic conditions have
been extremely favourable for this time of year. During foundation repair the
supervising agency has been particularly insisting on the quality of the works.
After the completion of the works we set out making tomographic records of the
foundations. The records have shown that on the left foundation side the
results are not satisfactory, so the order for the additional drilling has been
issued (20 boreholes), and additional grouting. Repeated records showed good
results, both in the right and the left foundation, and in such a way confirmed
the quality of the works. PCU has
required as well the detailed demobilization of the site, and restoring
of all the area into the original condition. The supervision of the Neretva
riverbed we have carried out separately in order for all the superfluous
elements to be removed. On 27.12.2001. a technical meeting of the
representatives of Unesco, technical assistance, and the representatives of the
PCU was held. At the meeting the following conclusions have been made:
In conformity with
the decions on the meeting among Project Coordination Unit, Project
Coordination Unit Technical Assistance and UNESCO-a held in Mostar on
27.12.2001., it is indispensable to carry out the following
core drillings with the additional core repair, in order to check the results
and the effects of the grouting procedures.
A) Those boreholes should be 8 meters deep, with 80 mm diameter at the
borehole end, inclined
with angle of 45 degrees. The positions of those boreholes should be as follows:
Left bank:
1.
Additional number of drillings 1 L, 30 cm upstream from the downstream edge of the left abutment wall;
2.
Additional number of drillings 2 L, in the middle of the distance between
the profiles 7L and 7-8L
3.
Additional number of drillings 3 L, 30 cm downstream from the upstream edge of the left abutment wall;
Right bank:
1.
Additional number of drillings 1 R, 20 cm downstream from the upstream edge of the right abutment wall;
2.
Additional number of drillings 2 R, in the middle of the distance between
the profiles 7R and 8R;
3.
Additional number of drillings 3 R, 20 cm upstream from the downstream edge of the right abutment wall;
The abovementioned locations
of the additional drillings are presented in three enclosures.
B) The following investigations are to be executed at
the repaired cores:
-
Detailed visual and
photographic survey of every restored core, with
special attention to grouting mass traces.
-
Monoaxial strength against
the core compression, 24 tests (4 per every borehole respectively, on every 2 metres of distance)
C) A detailed investigation on the
abovementioned operations should be submitted to the Project Coordination Unit
Technical Assistance and to UNESCO.
If we get deeper into the
analysis of the bridge foundation repair it may be concluded that the Yapi
Merkezi company has signed the abovementioned contract, but the complete
assignment it has taken over to «Karitaš» company. The equipment, personnel and
the technical staff belonged to the «Kartaš» company, only a small part of the
expert cadre has been composed of the Yapi Merkezi company experts.
III First stone cutting phase completion
PCU has set down to the
preparation of the next contract for the purchase of 200m3 of stone.
The contract for the purchase of the abovementioned quantities has been signed
on 08.05.2001. «Dent.Kamen» company Mostar. Supervision on the stone extraction
from the «Mukoša» quarry has been entrusted to the Geological Institute of
Bosnia and Herzegovina. Supervision on the cutting of the stone has been
entrusted to the Geological Institute of Bosnia and Herzegovina as well. On
12.03.2001. was held a meeting at World Bank premises in Sarajevo where were
present: Mr. Ahmet Gokce, Mrs. Vesna Frančić, Mr. Tihomir Rozić, Mr. Ante Šain,
Mr. Gilles Pequeux and Mr. Rusmir Ćišić. A conclusion has been made to take
into perspective the option that the supervision at the stone extraction should
be also carried out by the supervision on the cutting of the stone. The
aboveementioned agreement has been respected fully. As well it has been agreed
that Kara-Drvo company should cut additional 100m3 in accordance
with the set price for 260m3 . The abovementioned costs of the stone
acquision are covered by the city government, and the supervision on the stone
extraction in the quarry, taking into account that these resources do not enter
as the city participation in the projekt.. The stone cutting supervision costs
are covered by the City government, taking into consideration that they enter
as the city participation in the project. The final delivery amounting 200m3
was completed on 22.12.2001. Kara-Drvo company has cut 700 block pieces
so far. In order to cut the remaining 388 blocks it is necessary to make a
purchase of additional stone quantities 400 m3 , and to provide 50m3
of stone as an additional reserve in case of breakdown on some blocks.
The acquisition of the abovementioned 450m3 of the stone, and its delivery has to be
expeditious and quick. PCU on 08.11.2001. signed a contract for purchase of
300m3 with a standard price
of 1m3 = 1000,00 KM. The delivery of the abovementioned quantities
should set out in January 2002, taking into account that City government of
City of Mostar has to pay the advance payment in the amount of 150.000,00 KM.
The Dent-Kamen company owner is also
obliged to respect the agreed obligations with the reception of the advance
payment. If the stone is duly delivered, the remaining blocks will be
completely cut, and will be ready to be cut down to size with the help of the
chiselling procedure.
IV On 16.06.2001. a tender for prequalification of the companies for
building of the bridge was carried out
To the abovementioned tender the following companies registered
their interest:
Inter-invest company has thanked for the participation. Of the
remaining eight (8) companija, tender committee composed of :
has selected three companies,
and sent the final report into the World Bank for harmonization. With certain
amendments, comments on 11.12.2001. we received the World Bank approval for the
following three companies:
All the necessary project
documentation was sent on 14.12.2001 with the notice that it is necessary to
submit the bids for the building of the Old Bridge on 05.02.2002. at 14:00
hours. Project Coordination Unit will invest immense efforts to sign the
contract duly with the contractor in order for the bridge building to set out
according to the planned deadline.
IV Expression of interest for
the supervisor for the building of the bridge
On 16.06.2001. companies
submitted the prequalification documentation. Tender committee composed of:
met on 17.06.2001. To the
supervisor prequalifications twenty (20) companies registered their interest.
With the help of a detailed analysis of the submitted documentation of all the
registered companies, tender committee has selected six (6) companies:
The final report the tender
committee sent on 18.10.2001. into the World Bank. After certain corrections,
amendments and the like, World Bank 13.12.2001
approved the list of the companies for the supervisor.
On 27.12.2001. PCU sent to the
companies all the necessary documentation in order for them to prepare their
bidding documents.
NEIGHBOURHOOD
In the past period PCU Mostar
has launched two tenders belonging to the neighbourhood component:
On 27.08.2001. at 14:00 hours tender committee composed of:
implemented the opening of the
submitted bids for the neighbourhood component. Northeastern zone, Radobolja
riverbanks. The bids have been submitted by the following companies:
After a detailed analysis of
the submitted bids, tender committee has decided to entrust the abovementioned
assignment with Garant company – Mostar. World Bank has provided its approval
for the abovementioned company on 15.11.2001, so the PCU on 27.11.2001. signed
the contract with the abovementioned company.
On 04.07.2001. a tender
committee meeting for the abovementioned assignment was held. The following
companies have registered its interest for the tender:
After a detailed analysis of
the submitted bids, tender committee has forwarded the final report to the
World Bank. On 15.11.2001. we received the World Bank approval for Kara-Drvo
company – Kiseljak. On 27.11.2001., PCU signed the contract with the
abovementioned company. Buka watermill works have been completed in full, so
that the tehnical take-over of the structure has been carried out as well.
-
During year 2002, PCU Mostar plans to realize (3-4) structures
belonging to the neighbourhood component, whereas the remaining structures we
plan to finish in year 2003.
-
Kriva Ćuprija building resources have been provided by the
government of Luxembourg, and the whole job of its building has been entrusted
with the office of Unesco in Sarajevo. For the building of Kriva Ćuprija a
public tender has been launched, and the assignment has been awarded to the
Garant company – Mostar. The works are under way, and we expect the completion
of the works within the specified deadline.
We would like to inform you as
well that the Herzegovina-Neretva canton and the City administration of the
city of Mostar have with their joint resources carried out the repair of the
Radobolja riverbed banks 120 metres long. They have expressed as well their
readiness to keep up the works in year 2002 in accordance with their abilities.
VI Mission of director Mr.
Lawrence Hannah-a and the World Bank members
Mission composed of Mr.
Lawrence Hannah, Ms. Maha Armaly and Mr. Ahmet Gokce stayed from 17th
to 21st September 2001. in Bosnia and Herzegovina, and they have
dedicated the majority of their time to PCU Mostar. Fundraising and the
financing plan of our project was the first item of the mission. Mr. Lawrence
Hannah has notified PCU Mostar that the governments of certain countries, as
well as the European Development Bank have expressed their readiness for
financing of our project. Additional funds amount 3.500.000,00 $. Taking into
consideration the comprehensive funds which have been provided so far, and they
amount 13.500.000,00 $, they enable
unimpeded work at the building of the bridge and the towers, in addition to eleven
(11) neighbourhood component structures. PCU Mostar has notified the World Bank
delegation that our project covers structures belonging to three peoples too.
World Bank delegation has
given its approval that the planned funds amounting 50.000,00 $ can be utilized
for the project documentation preparation for the structures in question. After
the World Bank mission, PCU has conducted talks with Aga Khan Foundation, Mr.
Amir Pašić who has launched the initiative that Aga Khan Foundation
participates as well with 50.000,00 $ in the project documentation preparation.
We believe that the comprehensive documentation will be prepared by 30.04.2002.
The collaboration of the PCU Mostar and Aga Khan Foundation is on the
exceptionally high level, thus providing guarantees for the success of the
realization of the assignment in question. We believe that the World Bank will
provide as well the remaining funds for the building of the structures
belonging to the three peoples. With the building of the structures in
question even bigger and better
collaboration of the peoples in this area will be created.
Collaboration with the city
administration of the city of Mostar
PCU Mostar has prepared the
budget for the 2002., and it has duly submitted the budget to the city
administration for its adoption. In conversations with the mayor Mr. Neven
Tomić and the deputy mayor Mr. Hamdija Jahić, we have pointed out that the
provision of the planned funds for 2002. constitutes a very important factor in
the realization of the planned assignments. In 2002. begins the building of the
bridge, the towers, and one part of the neighbourhood component structures. We
have announced the start of the works as well on the structures belonging to
the three peoples, building of the UKD Napredak in Mostar. We would like to
point out the acquisition of the remaining stone quantities, and its cutting
down to its appropriate size. World Bank mission has completely prepared a
detailed analysis of the funds for: the bridge, towers and the neighbourhood
component. Material expenses of the PCU are extremely high as well, and in particular
while preparing documentation for certain tenders such as the one for the
building of the bridge, bridge supervisor, then office material acquisition,
salaries, taxes, overheads and the like. In order for the PCU Mostar to duly
meet its obligations, a sum amounting 10.000,00 $ is needed to be provided by
the city government. Taking into consideration the budget for year 2002, the
obligations of the city government are very high, so we are afraid that the
funds will not be provided on time.
Public relation marketing of the project
Public relation marketing of
the project is considered as the weakest link in its realization. In addition
to shortage of the financial funds for this purpose a big problem constitutes a
lack of cadre which would be able to present such a big and important project
in regard of marketing. We think that the arrival of the World Bank experts for
marketing, as well as its lenghthy stay and work with local marketing experts
would yield fruit. This point is particularly accentuated for the forthcoming
period 2002/2003. when building of the bridge, towers, and the other structures
begins. PCU is ready to help within its abilities (office, table, computer,
office supplies and the like). That is why we ask you consider the possibility
of solving of this problem.
Collaboration with Aga Khan Foundation, World Monuments' Fund
and UNESCO
We have to point out that the
collaboration with Aga Khan Foundation, and Mr. Amir Pašić and his team in
Mostar is exceptionally good. A young team of experts who work in the office of
Aga Khan Foundation in Mostar make big efforts in preparation of the project
documentation for the neighbourhood component, implementation of supervision of
specific structures, and they build certain structures with the Aga Khan
Foundation funds. City administration, PCU Mostar, Aga Khan Foundation have
launched big activities regarding project documentation preparation in the
field of infrastructure of the old city part, then environmental studies, which
we deem to be a very important factor for the whole project. Aga Khan
Foundation; PCU, and the representatives of the department for infrastructure
of the city administration, hold meetings every month with regard to the
problematic points. We have to point out that the infrastructure in the old
part of the city complies in its major part with the European normatives for
infrastructure. It is true that it is an extremely hard nut to crack,
especially if we bear in our minds that the World Bank in the city of Mostar
runs the project of water and sewerage, then this is the right time for taking
into perspective and solving of the infrastructure of the old city part. We
would like to pay a special tribute to the work of the department of Unesco in
Sarajevo. A professional work of Mr. Colin Kaiser, Prof. Langof, Mr.
Mulabegović, and Mr Šešum clearly contributes to the quicker solution of all
the emerged problems in the project. In addition to Kriva Ćuprija project, we
expect soon the realization of Turkish baths «Hammam». We believe that the
collaboration with Unesco expert team will become even better stronger in the
course of the building of the bridge and the towers.
At the end of this report we
would like to extend the warmest expression of gratitude to the World Bank
office staff in Sarajevo, to Mr. Joseph Ingram, and to Mrs. Vesna Frančić, who
invest big efforts in the realization of the project Old Bridge in Mostar.