REHABILITATION OF THE OLD BRIDGE

MOSTAR

 NEWSLETTER  10               APRIL 30, 2003                  MOSTAR, BOSNIA AND HERZEGOVINA  

 

Pouring the lead into channels

 

LEAD

 

Lead is known from ancient times (~ 1000. years B.C.). Its name comes from Latin word plumbum which means fluid silver.

 

Leaded cramps

 

It’s a soft, bleary grey metal which tarnishes on air from created protective layer of oxide and carbonate. It is resistant to corrosion and liquefiable only in oxidizing acids, like nitrite acid. It’s melting point is low, 327,4°C; significant amounts of poisonous lead vapour vaporize from melted lead even much below the melting point (1750°C).

                              

Test pouring of dowels with lead 

 

 

§          In the fine grained porous Eolithic surface of Tenelija the lead flows on a film of air on the stone surface pores: polishing of the channels is not necessary to encourage flow but it can be of help in problematic areas like low gradient channels.

 

§          Mortar layer in the stone joints will not interfere with channels for lead pouring, and will not obstruct them.

 

Thermometer

 

So, as you can see from above mentioned, great care should be given for the lead melting and pouring. This final step of the stone assembling is very important for the durability of the whole construction. If the temperature of lead is under the 370°C, there is a possibility that the channels become stocked by the cooling lead, and if it is over 430°C, later cracks are possible.

 

Returning the unused lead into the vessel

 

That was the reason for ordering special melting equipment. It consists of the metal vessel, easy to carry and equipped with the thermometer and metal can for pouring the lead into the gaps. It was made in workshop in Korčula, by Mr Vladimir Šeparović artist and expert in metal treatment.

 

 

Placing the rest of the stone blocks in that row was continued the same day. As it is planed, mounting of one arch row should be finished each day. It started with first five rows on the left bank, in order to equalize with the level on the right bank, where the rows weren’t even demounted because their condition was satisfying. After reaching the same level on both sides, alternately masonry will start. That way, weight and forces will be able to dispose smoothly. At the same time, lateral walls, fillings and inner rib will be filled.

 

Placing the stone

 

Necessary materials for all of these phases are already determined and prepared. They all were chosen first by their visual characteristics, and after that sent to the laboratory for further tests and examinations. For most of the materials, several samples had to be chosen for the laboratory tests, so only one of them could be approved.  All of them now have satisfied the quality compliance tests.

 

 

 

 

 

 

Principle of rows assembling

 

Pouring of lead into dowels

 

On the same place, in Komos, after chiselling of row is finished and its dimensions verified, holes for cramps and dowels are chiselled. Dowels are built into the blocks from upper side and poured with lead. After the Supervision finishes the inspection of row dimensions and chiselling quality, blocks are sent to the Old Bridge construction site.

 

Leaded dowels, ready to be built in

 

Great attention is given not to damage the blocks during transport, because by damaging a single block in a row we would have to start chiselling the entire row again. Knowing that the blocks are expensive and valuable, and that every repeated procedure means great delay in dynamic plan – precaution measures that are undertaken for safer transport are enormous.

 

Transport of blocks

 

 

Before proceeding to assembling works, it has to be pointed out that stones, (following ancient technique), should be connected with mortar and with additional metal strengthening devices that are anchored to stones by melted lead poured in purposely built slots (gaps).

 

For the above reason special expertise and devices for managing the lead are required and the following matters should be underlined:

 

§          Lead is strongly toxic: for melting and pouring works, adequate safety precautions are necessary.

 

§          It will be necessary to pour lead both off-site, and on-site. The risk of fire that may be caused during lead melting will be strongly limited by protecting the wooden deck.

 

§          Lead should be perfectly melted (370 – 420”C) before it is poured directly into stone channels with no waiting and no different route, this to avoid premature solidification.

 

Vessel for melting of lead

 

§          Exact composition of lead to be used will be determined and tested with the Quality Compliance Tests.

 

§          No water (not even hot water) will be preliminary poured in stone channels or slots to avoid vapour explosion when lead is poured: stone should be perfectly dry.

 

§          No thermal shock is suffered by the Tenelija stone due to lead pouring.

 

§          Stone channels and slots should be accurately cleaned from stone powder before lead is poured.

 

§          Prior the pour any trace of dirty or slag should be removed from the surface of the liquid lead.

 

 

Ceremony of placing the first stone

 

PLACING THE FIRST STONE INTO THE

ARCH OF THE BRIDGE

                                                             

On 14.04.2003, at 11 p.m., first stone of the bridge arch was ceremonially placed. Masonry started of left (east) bank of the Neretva river by placing the first upstream block. The Constructor arranged a special construction for this occasion, from where the guests could observe this act.

 

Attendant guests

 

Many guests attended the ceremony, the mayor of Mostar Mr. Hamdija Jahić, deputy mayor Mr. Ljubo Beslić, director of  Project Coordination Unit Mr. Rusmir Ćišić, project manager Mr. Tihomir Rozić, representatives of Supervision, of Contractor, and many journalists and TV networks. A large number of citizens of Mostar came and enhanced this grate moment with their presence.

 

Delegation on the centering

 

 

Ablation of blocks on the spot

 

In Komos, blocks are chiselled by rows: by templates prepared in advance for upstream and downstream forehead of the row, rough treatment of the stone is done first and then refined one. This procedure is very precise, because we know that the millimetre accuracy is required. No mistakes in this phase are allowed, because the assembling precision of the entire arch fully depends on this step.

 

Chiselling of rows in Komos

 

Every stone-cutter has its identification card and we know precisely for which phase he is qualified and what he can do. The best ones are working on finalisation of the visible stone surface, because it has to be the exact copy of the one that used to be on the old Old Bridge.

 

Supervision team is strictly following all of these works.

 

A row with chiselled holes for dowels

 

 

WEB CAMERA

 

Novelty in presentation of reconstruction of the Old Bridge is 2 web cameras which follow the works on the bridge 24 hours a day. The first one is placed on the left bank, beneath the studio terrace of painter Jusa Nikšić, and the other one on the right pillar of suspension bridge. In the close future we will add four more, on different places near the bridge and in Komos, which means that live pictures will be seen over the internet from six locations.   

 

Camera on the left bank

 

This is a common project of BH telecom and Bihnet, and their pages are available on the following addresses:

http://www.starimost.telecom.ba/indexie.htm         i

http://www.stari.bih.net.ba/indexie.htm

 

Background for the web page

 

 

WEB PAGE

 

In the last Newsletter, we announced that our web page is in the process of construction. Now we are happy to be able to give you its correct address:

http://www.erbu.mostar.ba/

 

The page is in two languages: from home page you can enter Bosnian and English version. In column ABOUT US you can get basic information about the company and the list of the most important bridges built so far. In the column CONTACT you can get address of the company or make a contact, and PRESS contains Newsletters and slide show which presents all that Contractor has done to date.  Addresses of the World Bank, UNESCO and PCU you can find under LINKS. PHOTO GALLERY has photos of different phases of reconstruction and FAQ answers frequently asked questions to the Contractor.

 

This NEWSLETTER was made in accordance with prevailing articles of the Contract No 002/2002 about the Rehabilitation of the

 Old Bridge, by ER-BU CONSTRUCTION / TURKE